Selections and allowances
When you choose tile, fixtures and finishes, how the showroom visit works, order lead times, and what happens if a choice costs more.
Selections are the finishes you choose: cabinets, counters, tile, fixtures, lighting, paint. You make most of them during pre-construction, at our showroom on Fox Street, so they are ordered in time for the week they are installed.
When each choice is due
| Selection | Due | Why |
|---|---|---|
| Cabinets | Before you sign the construction agreement | Lead times are often 8 to 10 weeks. |
| Windows and doors | Before you sign | Often 6 to 8 weeks. |
| Plumbing fixtures | Before rough-in | The rough-in is set to the fixture. |
| Tile and counters | Two weeks before install | Counters are measured on site once cabinets are in. |
| Paint colors | One week before paint |
Each due date is on your build calendar. A late choice can move the calendar; we tell you before it does.
Showroom visits
Saturdays, 9 to 1, by appointment, and weekdays by arrangement. Each visit is 45 minutes with Amara. Bring photos of rooms you like; we bring your allowance figures.
If a choice costs more
You see the difference against your allowance in a change order before anything is ordered. If it costs less, the difference comes off your final payment.