Selections and allowances

When you choose tile, fixtures and finishes, how the showroom visit works, order lead times, and what happens if a choice costs more.

Selections are the finishes you choose: cabinets, counters, tile, fixtures, lighting, paint. You make most of them during pre-construction, at our showroom on Fox Street, so they are ordered in time for the week they are installed.

When each choice is due

SelectionDueWhy
CabinetsBefore you sign the construction agreementLead times are often 8 to 10 weeks.
Windows and doorsBefore you signOften 6 to 8 weeks.
Plumbing fixturesBefore rough-inThe rough-in is set to the fixture.
Tile and countersTwo weeks before installCounters are measured on site once cabinets are in.
Paint colorsOne week before paint

Each due date is on your build calendar. A late choice can move the calendar; we tell you before it does.

Showroom visits

Saturdays, 9 to 1, by appointment, and weekdays by arrangement. Each visit is 45 minutes with Amara. Bring photos of rooms you like; we bring your allowance figures.

If a choice costs more

You see the difference against your allowance in a change order before anything is ordered. If it costs less, the difference comes off your final payment.