Your build calendar and the late-day credit
How the schedule in your agreement is set and kept, what moves it, and how the $250-a-working-day credit is applied.
Your agreement has a schedule with a substantial-completion date on it. We keep to it. If we finish late for a reason that is ours, we credit you $250 a working day against the final payment, as written in your agreement.
How the calendar is set
Owen writes the schedule week by week during pre-construction: demolition, framing, rough-in, inspections, drywall, finishes. Substantial completion means the space can be used for what it was built for, with only small punch-list items left.
What moves the date
| Reason | What happens |
|---|---|
| A signed change order that adds days | The days are added, as written on the change order. |
| Weather, for outside work | Days are added as the agreement sets out, and your superintendent logs each one. |
| A reason that is ours (a crew, a late order we placed, our mistake) | The date does not move. The credit applies. |
How the credit is applied
- $250 for each working day past the date, after the days above are added.
- Taken off your final payment; you do not have to ask for it.
- Shown as its own line on the final invoice.
Knowing where you are
Your superintendent posts a photo and a short note in your client portal every working afternoon, with the week you are in and what comes next.
Past projects. Every job is priced on its own
62 of 67 projects completed in 2025 finished on or before the date in the signed schedule.² One that did not, a Wheat Ridge bath, was planned at 6 weeks and took 7: one week late, credited $1,250.
² Substantial-completion date in the signed schedule, with days added by signed change orders and by weather counted as written in the agreement.