Commercial fit-outs and your opening date

How a tenant fit-out is scheduled backward from the opening date on your lease, and how the landlord, the permit and the inspections fit in.

For a commercial fit-out, the date that matters is printed on your lease. We plan the job backward from it, and the schedule in your agreement says so.

Working back from the lease

Weeks before openingWhat happens
16 to 12Pre-construction: drawings, the landlord’s review of them, and the permit set.
12 to 10Permit review by the building department. We file as soon as the landlord approves.
10 to 2The build: demising walls, ceilings, lighting, finishes, the accessible restroom.
2 to 0Final inspection, punch list, cleaning and your fixtures and furniture move in.

Your landlord

Most leases require the landlord to approve the drawings and our insurance before work starts. We send the landlord what they ask for and keep you copied. Kiri Tamatea, our commercial project manager, is the single contact for you and the landlord.

Working around other tenants

Noisy work is scheduled in the hours your lease and the building allow. Deliveries use the route the landlord sets.

Past projects. Every job is priced on its own

Ridgeway Bicycle Works, a 2,200 sq ft retail fit-out in Englewood, was built in 10 weeks against a 10-week schedule and opened on the date printed on the lease. Fixed price $168,500.

Permits and inspections are part of every job; the building department decides whether work passes inspection.