What your fixed price includes
What is inside the fixed price, what sits outside it, how allowances work, and the one way the price can change.
One fixed price, signed before we start. It changes only by a written change order that you sign first. Here is what it covers, line by line.
Inside the price
- Labor: our own crews for framing, finish carpentry and tile, and licensed trade partners for electrical, plumbing and mechanical.
- Materials named in the scope, and allowances for the selections you make later.
- Permits, permit fees and every inspection visit.
- Floor and doorway protection, daily cleanup, the dumpster and hauling.
- A superintendent on site every working day.
Outside the price
- Selections above the allowance in your agreement (you approve the difference in a change order).
- Anything the signed scope does not name.
- Conditions no one could see before we opened a wall. See “When we find something behind a wall”.
Allowances
An allowance is a set amount in the price for something you choose later, such as tile or light fixtures. If your choice costs less, the difference comes off your final payment. If it costs more, you see the difference in a change order before we order it.
Past projects. Every job is priced on its own
In 2025, change orders averaged 1.8% of contract value, owner-requested changes included.¹ The Harmon kitchen in Sloan’s Lake had a fixed price of $118,400 and one change order of $1,840 for two added outlets and a pantry pull-out.
¹ Total value of signed change orders divided by total original contract value, projects completed in 2025. Owner-requested changes included.