How design and pre-construction works

From the $350 design visit to a fixed price and a written schedule: the steps, the fees, and how both are credited when you build.

Before we build anything, we design it, price it and put it on a calendar. You see the fixed price and the schedule in writing before you sign the construction agreement. Both early fees are credited when you go ahead.

The steps

  1. Design visit ($350)
    90 minutes at your property with Amara Nwosu, our design lead. You get a written scope note within 3 working days. The $350 is credited in full against a signed Design & Pre-construction agreement.
  2. Design & Pre-construction (from $4,800)
    Measured drawings, the design to your approval (two revision rounds), the permit set, and selections at our showroom.
  3. Your fixed price and calendar
    Owen Pruitt, our director of pre-construction, prices every line and writes the build schedule week by week.
  4. The construction agreement
    One fixed price, the schedule, the four draws and the late-day credit, all in writing. The $4,800 is credited in full when you sign within 60 days.

How long it takes

ProjectPre-construction, typical
Kitchen or bath4 to 6 weeks
Basement finish4 to 6 weeks
Addition or second story8 to 12 weeks, including the permit review
Commercial fit-outSet to your lease and opening date

Permit review time depends on the building department, not on us. We tell you the current wait when we file.

Who owns the drawings

Your Design & Pre-construction agreement says who owns the drawings and how you may use them if you do not build with us.